Skip to main content
ElectraCore
LearnCalculatorsCircuit DesignerReferences
Saved
Educational use: ElectraCore supports learning and preliminary checks. It does not replace a competent electrician or engineer. Verify results, equipment data, and current local regulations before installation or live work.
Courses/Inspection & Testing/Continuity Testing

lesson · 8min · Lesson 8 of 36

Main and supplementary bonding continuity

Course syllabusCourse overview
01Test Sequence & Preparation
  1. ReadWhy test sequence matters: safety
  2. ReadDead tests before live tests
  3. ReadTest instrument calibration and leads
  4. ReadBS 7671 Appendix 6 test schedule
  5. quizPreparation quiz
02Continuity Testing
  1. ReadRing final continuity: three tests explained
  2. ReadProtective conductor continuity
  3. ReadMain and supplementary bonding continuity
  4. ReadContinuity test results: limits and recording
  5. exerciseContinuity exercise
03Insulation Resistance
  1. ReadIR testing principles: 500V, 1000V
  2. ReadTesting between live conductors and earth
  3. ReadLow IR readings: causes and diagnosis
  4. ReadElectronic equipment and IR testing
  5. quizIR testing quiz
04Earth Fault Loop Impedance
  1. ReadExternal impedance Ze measurement
  2. ReadTotal loop impedance Zs measurement
  3. ReadComparing Zs to Table 41.1 limits
  4. ReadCorrecting excessive Zs readings
  5. exerciseZs measurement exercise
05RCD Testing
  1. ReadRCD tripping current tests: half-rated and rated
  2. ReadRCD trip time testing at 1× and 5× rated current
  3. ReadMaximum trip time limits for different RCD types
  4. ReadRecording RCD test results
  5. quizRCD testing quiz
06Polarity & PFC
  1. ReadPolarity testing: dead and live methods
  2. ReadPFC measurement at origin and boards
  3. ReadVerifying PFC against device ratings
  4. quizPolarity and PFC quiz
07Certification & EICRs
  1. ReadEIC: Electrical Installation Certificate
  2. ReadMinor Works Certificate: when to use
  3. ReadEICR: periodic inspection
  4. ReadObservation codes C1, C2, C3, FI
  5. exerciseEICR coding exercise
08Final Assessment
  1. exerciseFull mock test schedule: complete it
  2. quizFinal written assessment
Lesson · 8min
EARTHING · TN-C-S (PME) vs TTTN-C-SsourceLPENMET (split N/PE)TTLNinstallation electrode; verify ADS and RCD requirements
Lesson contents 0%

In this lesson

PurposeCore theoryWorked exampleKnowledge checkSources

In this lesson

PurposeCore theoryWorked exampleKnowledge checkSources
0% read
ElectraCore lesson handout

Main and supplementary bonding continuity

Inspection Testing · Lesson 8 · Advanced

AdvancedReview: professional review pending

Purpose

Test main and supplementary protective bonding while distinguishing bonding purpose, conductor identity and parallel paths.

Before you beginSafe isolation · Protective conductors and circuit topology

Learning objectives

  • Plan a defensible sequence
  • Verify instrument and test boundary
  • Interpret topology from patterns
  • Record evidence without invented limits

Main protective bonding connects qualifying extraneous-conductive-parts to the main earthing terminal; supplementary bonding locally reduces touch voltage where required. Neither should be confused with functional bonding or an incidental pipe path.

CONTINUITY TOPOLOGY AND PATTERNCONTINUITY TOPOLOGY AND PATTERNORIGINCIRCUITtest pointinspect · isolate · prove · measure · interpret · restore · record

Core theory

Inspect conductor presence, route, size, identification, terminations and connection near the service entry as applicable. Determine whether the metalwork is actually extraneous using the installation assessment.

For a meaningful continuity measurement, isolate safely and manage parallel paths only where necessary and safe. Never disconnect main bonding while energized or leave it removed.

Record low-resistance continuity and reconcile it with conductor length/area and connections; a near-zero reading through parallel services may conceal a disconnected intended conductor.

Terms, symbols, and units
TermMeaningSymbolUnit
Main protective bondingConnection of extraneous-conductive-parts to the main earthing terminalNot applicableNot applicable
Supplementary bondingLocal equipotential connection used where requiredNot applicableNot applicable
Parallel pathAlternative conductive route influencing measurementNot applicableNot applicable
Worked exampleA bonding conductor measures 0.01 Ω in situ but rises open-circuit when its labelled end is safely disconnected for identification.

Assumptions: Values are supplied test data; The installation is safely isolated for dead testing.

  1. In situ: 0.01 Ω may be dominated by parallel metalwork.
  2. Identity: Open result shows the labelled conductor path itself is discontinuous or misidentified.
  3. Correct: Trace, repair/identify, reconnect and retest before restoration.

The initial low value did not prove the intended bonding conductor; repair and re-verify it.

Reasonableness check: The conclusion uses expected topology and comparative patterns; no single convenient reading overrides inspection or missing evidence.

Common mistakes
  • Starting live tests before dead-test defects are resolved
  • Calling a calibration label a pre-use functional check
  • Declaring a universal maximum continuity value without design context

Where this appears in practice

Initial verification combines inspection and ordered tests to prove protective measures before energisation; periodic work records the extent, limitations and observed condition.

SafetyTesting can create exposed conductors, remove protective paths or inject hazardous test voltage. Isolate and lock off, prove dead, control the area, discharge capacitance, reconnect every protective conductor and never leave a test link or bonding conductor removed.
Local code checkUse the edition of BS 7671 applicable to the work (noting the 2026 transition), current Guidance Note 3, the correct Appendix 6/model form, instrument manufacturer instructions, GS38, Electricity at Work Regulations and site safe system. Sequence may be varied only by competent risk-based planning with omitted/not-applicable tests and limitations explicitly justified and recorded.

Knowledge check

Can a low in-situ bonding reading prove the labelled conductor is continuous?

Not always. Parallel metallic paths can mask an open or misidentified conductor.

Answer: Not always. Parallel metallic paths can mask an open or misidentified conductor.

Practical exercise

Assess service metalwork, decide bonding applicability and design safe continuity checks for a supplied building.

Summary

  • Inspect and dead-test before avoidable live testing
  • Instrument validity has several independent checks
  • Continuity patterns prove topology and support later calculations

Sources and review

  • BS 7671 and Guidance Note 3: Inspection & Testing: IET; BS 7671:2018+A4:2026 / GN3 10th edition; transition rules apply; United Kingdom
  • Model forms for BS 7671: IET; A4:2026 and earlier applicable editions; United Kingdom
  • GS38: Electrical test equipment for low-voltage systems: HSE; Fourth edition; Great Britain
  • Ring-final continuity Step 3 resistance readings: IET Wiring Matters; 2022; United Kingdom

Editorial review date: 2026-08-22. Professional electrical review is pending.

Educational material for learning and preliminary checks. Verify current local requirements and exact equipment instructions. This lesson does not replace competent professional work.

Personal study record

Lesson notes

Ready

Notes are stored on this device unless you export them.