Skip to main content
ElectraCore
LearnCalculatorsCircuit DesignerReferences
Saved
Educational use: ElectraCore supports learning and preliminary checks. It does not replace a competent electrician or engineer. Verify results, equipment data, and current local regulations before installation or live work.
Courses/Inspection & Testing/Test Sequence & Preparation

lesson · 8min · Lesson 4 of 36

BS 7671 Appendix 6 test schedule

Course syllabusCourse overview
01Test Sequence & Preparation
  1. ReadWhy test sequence matters: safety
  2. ReadDead tests before live tests
  3. ReadTest instrument calibration and leads
  4. ReadBS 7671 Appendix 6 test schedule
  5. quizPreparation quiz
02Continuity Testing
  1. ReadRing final continuity: three tests explained
  2. ReadProtective conductor continuity
  3. ReadMain and supplementary bonding continuity
  4. ReadContinuity test results: limits and recording
  5. exerciseContinuity exercise
03Insulation Resistance
  1. ReadIR testing principles: 500V, 1000V
  2. ReadTesting between live conductors and earth
  3. ReadLow IR readings: causes and diagnosis
  4. ReadElectronic equipment and IR testing
  5. quizIR testing quiz
04Earth Fault Loop Impedance
  1. ReadExternal impedance Ze measurement
  2. ReadTotal loop impedance Zs measurement
  3. ReadComparing Zs to Table 41.1 limits
  4. ReadCorrecting excessive Zs readings
  5. exerciseZs measurement exercise
05RCD Testing
  1. ReadRCD tripping current tests: half-rated and rated
  2. ReadRCD trip time testing at 1× and 5× rated current
  3. ReadMaximum trip time limits for different RCD types
  4. ReadRecording RCD test results
  5. quizRCD testing quiz
06Polarity & PFC
  1. ReadPolarity testing: dead and live methods
  2. ReadPFC measurement at origin and boards
  3. ReadVerifying PFC against device ratings
  4. quizPolarity and PFC quiz
07Certification & EICRs
  1. ReadEIC: Electrical Installation Certificate
  2. ReadMinor Works Certificate: when to use
  3. ReadEICR: periodic inspection
  4. ReadObservation codes C1, C2, C3, FI
  5. exerciseEICR coding exercise
08Final Assessment
  1. exerciseFull mock test schedule: complete it
  2. quizFinal written assessment
Lesson · 8min
Lesson contents 0%

In this lesson

PurposeCore theoryWorked exampleKnowledge checkSources

In this lesson

PurposeCore theoryWorked exampleKnowledge checkSources
0% read
ElectraCore lesson handout

BS 7671 Appendix 6 test schedule

Inspection Testing · Lesson 4 · Advanced

AdvancedReview: professional review pending

Purpose

Use the applicable Appendix 6 schedule as a recording framework while selecting every test from the actual installation.

Before you beginSafe isolation · Protective conductors and circuit topology

Learning objectives

  • Plan a defensible sequence
  • Verify instrument and test boundary
  • Interpret topology from patterns
  • Record evidence without invented limits

Model forms help produce consistent evidence but do not replace engineering judgment. The design, protective measures and installation extent determine which inspections/tests apply and what values are expected.

SAFE TEST SEQUENCE AND EVIDENCESAFE TEST SEQUENCE AND EVIDENCEORIGINCIRCUITtest pointinspect · isolate · prove · measure · interpret · restore · record

Core theory

Record client/installation details, extent, design/construction/inspection responsibility, supply and earthing characteristics, protective devices, departures, limitations and schedules using the correct edition.

For each circuit record identifiers, conductor/protection data and actual results with units. Use N/A only when genuinely not applicable and state reasons where clarity is needed; never copy adjacent results.

Link instrument serials and test methods, resolve anomalies, sign only within competence/responsibility and retain controlled records/as-builts. The form's presence is not proof tests occurred.

Terms, symbols, and units
TermMeaningSymbolUnit
Appendix 6BS 7671 model certification/reporting forms and schedulesNot applicableNot applicable
DepartureIntentional variation assessed to provide no lesser safetyNot applicableNot applicable
N/ANot applicable, not shorthand for untestedNot applicableNot applicable
Worked exampleA circuit has no RCD, and its RCD time cell is blank while insulation resistance was not measured.

Assumptions: Values are supplied test data; The installation is safely isolated for dead testing.

  1. RCD: Mark RCD fields N/A if legitimately not applicable.
  2. IR: A blank IR cell does not justify omission.
  3. Record: Test IR or document an agreed limitation/valid reason; never imply satisfactory evidence.

RCD can be N/A; missing IR needs test evidence or explicit defensible limitation.

Reasonableness check: The conclusion uses expected topology and comparative patterns; no single convenient reading overrides inspection or missing evidence.

Common mistakes
  • Starting live tests before dead-test defects are resolved
  • Calling a calibration label a pre-use functional check
  • Declaring a universal maximum continuity value without design context

Where this appears in practice

Initial verification combines inspection and ordered tests to prove protective measures before energisation; periodic work records the extent, limitations and observed condition.

SafetyTesting can create exposed conductors, remove protective paths or inject hazardous test voltage. Isolate and lock off, prove dead, control the area, discharge capacitance, reconnect every protective conductor and never leave a test link or bonding conductor removed.
Local code checkUse the edition of BS 7671 applicable to the work (noting the 2026 transition), current Guidance Note 3, the correct Appendix 6/model form, instrument manufacturer instructions, GS38, Electricity at Work Regulations and site safe system. Sequence may be varied only by competent risk-based planning with omitted/not-applicable tests and limitations explicitly justified and recorded.

Knowledge check

May N/A be used for a test that was simply inconvenient?

No. It means the test does not apply to that circuit/protective measure.

Answer: No. It means the test does not apply to that circuit/protective measure.

Practical exercise

Audit a partly completed schedule for units, applicability, copied values, missing evidence and edition mismatch.

Summary

  • Inspect and dead-test before avoidable live testing
  • Instrument validity has several independent checks
  • Continuity patterns prove topology and support later calculations

Sources and review

  • BS 7671 and Guidance Note 3: Inspection & Testing: IET; BS 7671:2018+A4:2026 / GN3 10th edition; transition rules apply; United Kingdom
  • Model forms for BS 7671: IET; A4:2026 and earlier applicable editions; United Kingdom
  • GS38: Electrical test equipment for low-voltage systems: HSE; Fourth edition; Great Britain
  • Ring-final continuity Step 3 resistance readings: IET Wiring Matters; 2022; United Kingdom

Editorial review date: 2026-08-22. Professional electrical review is pending.

Educational material for learning and preliminary checks. Verify current local requirements and exact equipment instructions. This lesson does not replace competent professional work.

Personal study record

Lesson notes

Ready

Notes are stored on this device unless you export them.