Skip to main content
ElectraCore
LearnCalculatorsCircuit DesignerReferences
Saved
Educational use: ElectraCore supports learning and preliminary checks. It does not replace a competent electrician or engineer. Verify results, equipment data, and current local regulations before installation or live work.
Courses/Solar PV & Renewables/Grid Connection

lesson · 8min · Lesson 23 of 29

Export limitation and smart export tariffs

Course syllabusCourse overview
01PV Physics & Panel Technology
  1. ReadPhotovoltaic effect: how a cell works
  2. ReadMonocrystalline vs polycrystalline vs thin-film
  3. ReadPanel specifications: Voc, Vmp, Isc, Imp
  4. ReadTemperature and irradiance effects
  5. quizPV physics quiz
02System Design & Sizing
  1. ReadSite survey: roof orientation, shading, pitch
  2. ReadString sizing: voltage and current matching
  3. ReadSeries vs parallel string configurations
  4. ReadYield estimation: kWh/kWp calculations
  5. exerciseSystem sizing design exercise
03Inverters
  1. ReadString inverters: topology and MPPT
  2. ReadMicroinverters and power optimisers
  3. ReadHybrid inverters for battery systems
  4. ReadInverter selection criteria
  5. quizInverter quiz
04Battery Storage
  1. ReadBattery chemistries: LFP vs NMC
  2. ReadBattery sizing for self-consumption
  3. ReadAC vs DC coupled systems
  4. ReadBattery safety and installation requirements
  5. exerciseBattery sizing exercise
05Grid Connection
  1. ReadG98: systems up to 3.68kW per phase
  2. ReadG99: larger systems, DNO approval
  3. ReadExport limitation and smart export tariffs
  4. ReadGeneration and export metering
  5. quizGrid connection quiz
06Installation & Commissioning
  1. ReadRoof mounting systems: rail and clamp
  2. ReadDC cable sizing and routing
  3. ReadCommissioning and functional testing
  4. quizFinal assessment
Lesson · 8min
Lesson contents 0%

In this lesson

PurposeCore theoryWorked exampleKnowledge checkSources

In this lesson

PurposeCore theoryWorked exampleKnowledge checkSources
0% read
ElectraCore lesson handout

Export limitation and smart export tariffs

Solar Pv · Lesson 23 · Advanced

AdvancedReview: professional review pending

Purpose

Design export limitation as a fail-safe network-control function, distinct from a smart export tariff.

Before you beginPV array and inverter design · Protection, isolation and testing fundamentals

Learning objectives

  • Identify the governing boundary
  • Trace energy and measurement paths
  • Apply evidence in the required sequence
  • Recognise unsafe assumptions

A G100 export-limitation scheme measures power at the agreed boundary and controls generation or storage so export remains within an approved limit. Its safety and failure behavior matter as much as its normal setpoint.

GRID CONNECTION AND EXPORT CONTROLGRID CONNECTION AND EXPORT CONTROLMODULEMPPTcold Voc · hot Vmpirradiance · temperature · shading · exact product limits

Core theory

Confirm CT/meter location, phase coverage, orientation, communications, response time, control hierarchy, inaccessible settings and behavior on sensor, communications or controller failure.

Include every generator and storage device that can affect boundary export. Prove the scheme across import, export, rapid load loss, full generation and credible failure states.

DNO approval and any witness/type-test evidence are separate from the commercial export tariff. A tariff cannot increase approved network export capacity.

Terms, symbols, and units
TermMeaningSymbolUnit
G100ENA recommendation for customer export-limitation schemesNot applicableNot applicable
Fail-safeMoving to a defined safe state on a credible failureNot applicableNot applicable
Export limitMaximum permitted power flow from customer installation to networkNot applicableNot applicable
Worked exampleA site generates 8 kW, consumes 3 kW and has a 4 kW approved export limit.

Assumptions: Values are supplied design inputs, not universal limits; Current DNO and product evidence will be checked.

  1. Uncontrolled: Boundary export would be 8 − 3 = 5 kW.
  2. Required control: At least 1 kW of generation must be curtailed or absorbed.
  3. Verify: Test rapid load loss and sensor/control failure, not only this steady state.

The controller must reduce boundary export by at least 1 kW in this state and remain compliant during transitions/failures.

Reasonableness check: The conclusion follows the connection point, aggregate plant and declared equipment rather than a marketing label.

Common mistakes
  • Treating 3.68 kW as a timeless universal threshold
  • Assessing each inverter separately instead of aggregate behavior at the connection point
  • Confusing a portal reading with settlement-grade metering

Where this appears in practice

A complete PV installation coordinates mechanical support, DC design, network permission, export control, metering, inspection, testing and handover.

SafetyIlluminated PV remains energized after AC isolation. Use the documented isolation, proving, connector, roof-access and test procedure; never disconnect loaded DC connectors or short a string casually.
Local code checkConfirm the current issues/amendments of G98, G99 and G100, the exact Connect Direct type-test record, the relevant DNO process and permission, current BS 7671 Section 712, MCS requirements where applicable, IEC 62446-1, manufacturer instructions, structural/fire design and metering/tariff rules. Network permission, electrical compliance, export payment and product monitoring are separate evidence streams.

Knowledge check

Does an export tariff prove G100 compliance?

No. Commercial payment and the approved technical export-limitation scheme are separate.

Answer: No. Commercial payment and the approved technical export-limitation scheme are separate.

Practical exercise

Draw a G100 measurement/control diagram and a failure-state test table for PV plus battery storage.

Summary

  • Use the current rule and exact product record
  • Assess the whole installation at the connection point
  • Commissioning evidence is broader than successful generation

Sources and review

  • Engineering Recommendation G98: Energy Networks Association; Current issue and amendment must be confirmed; Great Britain
  • Engineering Recommendations G99 and G100 / Type Test Register guidance: Energy Networks Association; Current issue and Connect Direct status must be confirmed; Great Britain
  • IEC 62446-1:2016: PV systems: documentation, commissioning tests and inspection: IEC; 2016 + AMD1:2018; International
  • Health and safety in roof work (HSG33): HSE; Fifth edition; Great Britain

Editorial review date: 2026-08-22. Professional electrical review is pending.

Educational material for learning and preliminary checks. Verify current local requirements and exact equipment instructions. This lesson does not replace competent professional work.

Personal study record

Lesson notes

Ready

Notes are stored on this device unless you export them.